Work at Hamon ?

31 July 2020

RWE Little Barford Power Station : Completion of First Major Milestone during Lockdown

  • Wet Cooling Towers
#

Hamon were awarded a contract in May 2019 to convert RWE Little Barford Power Station, UK to a conventional plume abated Cooling Tower. 

The power station cooling towers comprise two banks of 14 cells (28 cells total) fed by 14 risers (2 cells per riser). The total flow rate is 41,832m3/hr. The cooling tower was originally designed with a wet / dry pack in crossflow configuration to provide a design plume point of 4°C and 92% RH.

Hamon received the RFQ to repack this cooling tower with the view to restoring the original design duty conditions. As an option, Hamon offered to convert the cooling tower to a more conventional induced draught, plume abated design with tube bundles. The conversion is to be undertaken on a riser-by-riser basis always leaving 26 cells operational.

 

 

 

Due to problems with the original design, the pack could not be cleaned without major intervention and the maintenance of the wet / dry pack cores was almost impossible. As a result, the Client had planned for condition based, repacking of these towers approximately every 10 years. With the current pack condition, we established that the Cooling Water was around 3.4K higher than the original design criteria. The conversion offered an improvement in performance expressed as an improvement against the original design cold water temperature and the ability to adopt conventional cleaning and other maintenance regimes, whilst also improving Legionella Control compliance. 

Site activities commenced in January 2020 and there have been many challenges. Hamon works were suspended for just 3½ weeks during the COVID-19 pandemic. 

The first riser has now been completed and with successful interim testing (thermal, plume and drift loss) by Hamon was completed 19th June 2020. The tests show that we have achieved the guaranteed criteria for thermal, plume and drift loss for this first riser. 

Health & Safety: to date we have zero Lost Time Accidents and zero First Aid Incidents.

To know more about the challenges and solutions, read the full case study

  

 

 

This site uses cookies. By continuing to browse the site, you are agreeing to our use of cookies.
OK